Initiation [This step includes the intake of the project to define the projects purpose, high level scope and possible resource needs prior to governance approval. ]
20% complete, updated on Wed 11/18/20 1:40 PM by Sara Vance
Changed Percent Complete from 0% to 20%. Changed Health from None - No health has been set to Green - On track.This week the team did backlog grooming of known open items. The group go through Fall 2020 and Spring 2021. Area's were identified where more resources may be needed and several things have been moved to in progress or on hold. Weren't able to update few things things and ask the group to go in and update the cards with progress or more information if known. Thanks,Sara
This workspace is to understand and review pending projects, enhancements and tickets for the Student Affairs team.