Application Services Release Management

0%

Status

Close [This project phase included close meetings, recording lessons learned, organizing project documentation, client sign off, team celebrations and closure of any tasks. ]

0% complete, updated on Mon 1/22/24 9:40 AM by Ed Jacobs

Changed Percent Complete from 100% to 0%.
Changed Health from None - No health has been set to Green - On track.

Details

Dates
Mon 11/1/21 - Tue 1/22/30
Acct/Dept
Application Services
Type
Project & Portfolio Management / Operational Work
Health
Green - On track
Created
Mon 11/8/21 10:22 AM
Modified
Mon 1/22/24 9:40 AM
Closed
Mon 1/22/24 9:30 AM

Manager

Alternate Manager(s)